Monday, August 11, 2014

Aroha Restaurant: Floors are In, Sign is Up!...What's Left?

The clock is really ticking down now! Later this week, we'll be announcing our official opening date, along with a few signature menu items. I am eager to announce it but I also know that once we do, everything else has no choice but to fall into place.

For those of you wondering where we're at right now and why we haven't announced our opening date yet, here is what we're waiting on:

• The gas company. We've been in contact with them for the past month to have the gas line run to our restaurant so we can use our stoves. This is probably the most important thing on our list right now, as you can imagine! They're working on it and hopefully this week it will be completed.

• Internet. We're waiting to get the lines installed. Again, this week should be the week.

• Our Furniture. This I can give a definitive time table on! Our indoor furniture will be ready tomorrow, and our outdoor furniture will be ready on both Wednesday and Thursday!

This past week has been incredibly intense. As the countdown begins, it feels a little bit like an episode of 24. There's only so much time left in the season and still so much we need to complete by the end. It's all absolutely doable. If it wasn't, we would hold off on deciding our opening date. However, we have a date in our heads, and we are 95% sure that we'll be ready to open by then. It still doesn't stop us from having that ticking clock sound in our heads, though! In reality, our list is a lot less than it was a month ago. We started last month with a list of at least 40 reminders and this month, we have about 10 to complete. The hardest part for me is most of the things we're waiting on now, relies on other people. As confident as I am (deep down inside!) that they will be done by their deadlines, relying on other companies to get a job done always feels like a wildcard to me. But honestly, there's nothing I can do at this point to make these things happen any sooner, and I have to accept that.

Last week, we had our first round of interviews and I am beyond excited to say that we hired the shift leader for our front of house team! We will be interviewing a lot more employees this week and can't wait to have the full team together. In other news, we also met with our supplier and rep from World Wide Produce, Lynde, and gave her a list of all of the items we're going to need. There were some very interesting garnish items she had that we are also eager to try and hopefully serve to our customers! Last night, we received a copy of our wine list. We're ecstatic to announce that 60% of our list will offer New Zealand wines and all of our By the Glass wines will be from New Zealand! Besides a 60% New Zealand wine selection, all of our beers will be from New Zealand, as well as our soda and juice selection provided by Aroha Drinks. Speaking of, we got a sampler pack in the mail over the weekend:

Aroha Drink flavors include Sparking Blackcurrant, Sparkling Feijoa, Sparkling Rhubarb,
Ginger Lemon & Honey, Sauvignon Blanc & Saffron, and Elderflower & Green Currant
Construction wise, the flooring has all been installed, the LED lights are up on the soffits, the outdoor fountain is up and running, and the fencing has been put in for our patio! In the upcoming weeks, we will be getting our countertops, shelves, cabinets, and host station! We also received our menu booklets the other day. Our pet rabbit, Willow, is excited about all of the boxes of menus in our entryway! She's been enjoying climbing on them and even tried to open them herself.

The outdoor fountain

Over the weekend, we set up our phone. We had quite a fun time trying to get the answering machine to work! After Gwith recorded the greeting five times to get it perfect, we realized he recorded it in the wrong spot somehow. So, it took another five to ten tries just to get it right! We are happy to say the recording is finished, our phone is in, and it no longer makes loud obnoxious noises and speaks when someone calls to leave a message! YAY! The unfortunate part is, once we announce our opening date, we'll have to re-record the message...and then re-record it again when we open. It's okay though. He's doing it, not me...which means I just get to stand next to him and be entertained!

The best news of the week however is that our sign went up on Friday! We are so pleased with how it turned out! When we first looked at the property, this was the very first thing I envisioned. It's been amazing watching the entire vision of the restaurant come to life but seeing the sign, exactly where I pictured it back in March, is amazing.


As of today, this is what our restaurant looks like, pre-furniture (except for the outdoor couches and end table currently sitting inside!), with the complete wood floors and LED lights turned on!


We are so excited to finish the construction process and focus on our future customers and service! Stay tuned for the opening date and soft opening announcements!